A project's Timeline shows its tasks as bars across the days they run, from each task's start date to its due date, with arrows from each task to the tasks waiting on it. The Projects page shows every project you're in on one page: how far along each one is, what's late, how its people last said it was going, every project on one timeline, and who has too much to do each week.
The timeline
Open a project and choose Timeline, next to List and Board.
- Each task is a bar from its start date to its due date. A task with only a due date is a one-day bar on that day.
- Tasks are grouped by status, in the board's order. View groups them by assignee instead, or not at all, and can hide done tasks.
- Days, Weeks and Months change the scale. Today brings today back into view. The line down the timeline is today.
- An open task whose due date has passed has a red outline.
- Cancelled tasks aren't shown. Subtasks stay inside their task: open it to see them.
- Click a bar to open the task.
The timeline opens with the plan in view: today and the whole plan when they fit, and otherwise the tasks nearest today.
Moving tasks
A project's admins can change dates on the timeline:
- Drag a bar to move the task. Its start and due dates move together and keep their times of day.
- Drag either end of a bar to change when it starts or when it's due.
- Unscheduled lists the open tasks with no dates. Drag one onto a day to make it due that day at 17:00.
- From the keyboard: press Tab to reach a bar, then ← and → move it a day, Shift with an arrow changes when it's due, and Enter opens it. Several presses in a row are saved as one change.
- Esc while dragging puts the bar back.
Each change shows at once on the board and the list as well, and goes into the task's history. If a change can't be saved, the timeline puts the task back and says why. Everyone with the project open sees a new date as soon as it's saved, without refreshing.
On a phone, the timeline shows the plan. Tap a task to change its dates.
Dependencies
A task can wait on other tasks of its project. Most often it can start once they're done (finish to start), and that's what a new dependency is. The timeline draws an arrow from each task to the task waiting on it.
- On the timeline, point at a bar and drag the small handle at its end onto the bar of the task that waits on it. Esc while drawing cancels.
- In a task's panel, Dependencies lists what it's waiting on and what it's blocking, each with how it waits. Waits on… adds one from the project's tasks; the × on a row takes one off, and the name opens that task.
- An arrow turns red when the plan can't be kept as it stands: for finish to start, when the waiting task starts before the other is due. Finished work never turns one red.
- A task still waiting to start on open work shows a lock with how many it waits on, on the board, in the list and on its bar.
Kinds of dependency, and lag
A project's admins can change how a task waits. In its panel, press the words beside the other task's name (Finish to start, to begin with), choose a kind and a lag, and press Save.
| Kind | The waiting task can't… | For example |
|---|---|---|
| Finish to start | start until the other finishes | Build starts once the design is done |
| Start to start | start until the other starts | Writing the docs starts once the build has |
| Finish to finish | finish until the other finishes | Testing ends after the build does |
| Start to finish | finish until the other starts | The old rota runs until the new one starts |
A lag adds days: finish to start with a lag of 2 leaves two days between the tasks, for a review or for paint to dry. A negative lag lets them overlap: −2 lets the waiting task start two days before the other is due. Lags are whole days, up to 365 either way. The panel says what you've chosen in a sentence, such as "Build can't start until 2 days after Design finishes", before you save.
The arrow runs between the ends the kind ties: from the other task's start or end to the waiting task's start or end. Only finish to start puts a lock on a task: it can't start while the other is open. With the other kinds, both can be under way at once.
When you move a task later, the tasks waiting on it move along, just far enough to keep to each kind and lag. Each keeps how long it runs and its times of day, and the tasks waiting on those move too. Nothing moves earlier, finished tasks and tasks without dates stay where they are, and a clash you didn't cause by this move is left for you to see. Every task moved along says so in its history. To move only the task you drag, turn off Move waiting tasks along in View.
A task can't wait on itself, on a subtask, on a task of another project, or on a task that already waits on it, however indirectly: that would be a loop, and OneCamp says so. A project's admins add, change and remove dependencies; the history of the waiting task records each one added or removed.
Your client's timeline
A client who follows the project from its client link can switch their page from Board to Timeline. They see the same bars, read-only, and open a task to read it.
The projects overview
All projects, at the top of Projects in the sidebar, lists every project you're in. Go to Projects in Ctrl/⌘ K opens it too. On a phone, tap your organization's logo at the top left and choose Projects.
| Column | What it shows |
|---|---|
| Health | What the project's latest update said: On track, At risk, Off track, On hold or Done |
| Done | The share of its tasks that are done |
| Tasks | How many are open, overdue, due this week and done, counted in your own time zone |
| Last update | When its latest update was posted |
Needs attention narrows the list to the projects that are off track, at risk, or have overdue tasks. Sort by name, by what needs attention first, by the least done, or by the oldest update. Your choice is remembered. On a phone, each project is a row with its health, its tasks and a progress bar.
A project's health comes from its updates. See Project updates.
Every project on a timeline
On the projects overview, choose Timeline next to Table. Each project is one bar from the first day of its tasks to the last, filled as far as its tasks are done and coloured by its health. Click a bar to open that project's timeline. Search and Needs attention narrow it the same way as the table.
Workload, the third view, shows who has how much to do each week across all of these projects. See Workload.
Goals, the fourth view, lists the workspace's goals with how far each has got against its time. See Goals.
Reports, the fifth view, count what got done and what came in each week, and what's open and overdue by project, person and priority. See Reports.
The timeline, the projects overview, dependencies and the workload are on every plan, the free one included.